ETI training...

Image
   Condition For issuing tender&LOI  Financial approval from MD are compulsory condition for issuing LOI  Financial approval from MD is not necessary to open tender Different Committee and Financial Power TWC-MD,Director(Operation,W&P,SLDC,C&P,Finance),Chief(Planning,Energy system,PPMM) BOD-Director(Operation,W&P,Finanace, Appraisal ETF MDSPC CSPC No of Disc required in Transmission Line   Operating Voltage Suspension Tension 11Kv 1 1 33Kv 2 3 66Kv 5 6 132Kv 9 10 220Kv 14 15 400Kv 21 22 765 Kv Line contain two signal frequency Power Frequency 50Hz Carrier Frequency (3-148KHz) Electricity status in U.P Peak demand 23000MW Total transmission Line Length 14000Km Total no of substation 585 Power Transfer Capability Distance B/w two substation Voltage Rating 50Km 100Km 200Km 300Km 66Kv 22MW 11Mw 5.5Mw 3.6Mw 132Kv 120Mw 60Mw 30Mw 20Mw 220Kv 400Mw 200Mw 100Mw 67Mw 400Kv 1500Mw 750Mw 375Mw 250Mw Record of Uttar pradesh in Power sector First 210Mw & 5...